Net metering lets a K-Electric customer with a solar system export surplus power to the grid and receive credit for it. The rules changed in 2026, so older guides, including many still ranking on Google, no longer describe how it works. This is a summary of the current K-Electric framework. Rules and fees can change, so confirm the details with K-Electric before you apply.
What Changed in 2026
In February 2026 NEPRA replaced the 2015 net-metering regulations with the Prosumer Regulations, 2026. The model is now called net billing, and the same national rules apply to every distribution company, including K-Electric.
- The old one-to-one unit swap is gone. Units K-Electric supplies to you are billed at your applicable tariff, and units you export are bought at the national average energy purchase price, which is lower than the retail price and which NEPRA can revise.
- If the value of your exports is greater than the value of your imports in a billing cycle, the credit is carried to the next cycle or paid to you quarterly.
- The agreement term is five years from commissioning, renewable for further five-year terms by mutual consent.
- Agreements signed under the old rules keep their old billing terms until they expire. That protection ends if the system is materially modified so that its maximum output changes.
In practice, exporting power is now worth much less than using it yourself. That favours a system sized to cover your daytime use, and it makes batteries and daytime load shifting more attractive than before.
Who Can Apply and System Size Limits
- The regulations name 3-phase 400 V and 11 kV consumers as eligible applicants. If you have a single-phase connection, ask K-Electric whether it qualifies
- Systems from 1 kW up to 1 MW are eligible
- Your solar capacity cannot exceed your sanctioned load
- Systems of 25 kW or below do not need NEPRA concurrence: the distribution company approves them and no concurrence fee applies
- Systems above 25 kW need NEPRA concurrence and a one-time fee paid to NEPRA
- Systems of 250 kW or above need a load flow study by the distribution company or a PEC-registered consultant
- An application is not accepted if the distributed generation already connected to your distribution transformer has reached 80% of its rated capacity
Equipment Requirements
- Grid-tied inverters that are PEC-certified and that comply with the UL 1741 interconnection standard
- Anti-islanding protection, which shuts the inverter down when the grid is off, and automatic prevention of reconnection until supply is stable
- A manual disconnect device with a visual break
- A bi-directional meter (or two meters), installed through K-Electric
- Surge protection devices (SPDs)
How to Apply: Step by Step
- 1Choose an approved, PEC-certified solar installer. The category the installer needs depends on the size of your system.
- 2Submit the application through the K-Electric net metering portal. A processing fee applies.
- 3K-Electric carries out a technical site survey and reviews your single-line diagram (SLD). This stage typically takes a few weeks.
- 4Once the application is approved and the licence fees are cleared, K-Electric installs the bi-directional meter.
- 5After the meter is installed and the system is commissioned, you start exporting.
From application to meter installation, the process commonly takes from one to two months, and sometimes longer, depending on K-Electric's workload and whether your documents are complete. The regulations set maximum times for each step: the company must acknowledge your application within five working days, finish its initial review within fifteen, sign the agreement within seven and install the connection within fifteen of your payment, so a delay beyond those limits is worth raising.
A system connected to another distribution company, such as IESCO or LESCO, follows the same national regulations. If you are in Islamabad, Rawalpindi or Lahore, see our IESCO and LESCO guides.
Net metering in Islamabad and Rawalpindi: IESCO process and 2026 rules →
Net metering in Lahore: LESCO process and 2026 rules →
Is Net Metering Still Worth It?
For most homes, the biggest saving comes from using the solar power you generate, not from exporting it. A well-sized system that covers your daytime consumption still cuts your bill substantially. A larger system built mainly to export earns much less than it used to. This is why system design matters more than ever: the right size depends on your usage pattern, not just your roof space.
What to Ask Your Installer
- Which K-Electric rules apply to my application, and who prepares and submits it?
- Is the inverter certified and does it have anti-islanding protection?
- How is the system sized for my daytime usage, given the lower export credit?
- What happens if K-Electric asks for changes or rejects the application?
- Do you recommend batteries, and what would they cover?
MaxGreen Energy designs systems for Karachi homes, businesses and factories and handles net metering applications. We offer a free site assessment.
Solar installer in Karachi that handles K-Electric applications →
Get Your Free Solar Survey Today
Our team will visit your site, assess your energy needs, and provide a custom NEPRA-compliant proposal — absolutely free.
Book Free Survey